Civil Electrical Project for the Nuclear Island of Units 3 and 4 of Mochovce NPP 3. and 4 of Mochovce NPP

Project duration: March 2010 – December 2024

The civil electrical project was one of the most significant in its scope in our company’s history, right after the Technological Delivery for the Mochovce NPP Completion project. On December 3, 2024, this chapter was concluded by signing the Acceptance Protocol for Part 2 of the Civil Electrical Project. The final transfer of the work for permanent use, encompassing the design, supply, installation, testing, and commissioning of the electrical components for the nuclear island of Units 3 and 4 of Mochovce NPP. 3. a 4. bloku JE Mochovce v časti jadrový ostrov.

Working in the switchboard, wiring

Our activities:

Project and Assembly Documentation:
  • Execution project documentation for lighting, heavy-current distribution systems, lightning protection systems, and earthing and as-built documentation
  • Test programs
  • Inspection and Test Plans for delivery, assembly, and tests, Assembly Organisation Plans, technological procedures and manuals
  • Reports, and background documentation for junction boxes, switches, sockets, cables, and earthing
  • Redline markup, accompanying technical documentation, and as-built design
  • OH&S program, training program for the Client’s staff, time schedules, etc.
Coordination Activities:
  • Coordination of works and tests including follow-up activities
  • Coordination of subcontractors’ schedule with the Client’s schedule
  • Coordination of assembly and tests
  • Daily monitoring and evaluation of schedule and its updates
  • Preparing fire permits, and work permits
  • Coordination of safety on the construction site
  • Quality assurance
Procurement, Installation, and Testing:
  • Anchor plates to support items and cable routes
  • Lighting fixtures and switches
  • Distribution boards and welding boxes
  • Supplying, laying, connecting, and testing power cables
  • Testing working, standby, and emergency lighting outlets both inside and outside the hermetic zone of the main reactor building
  • Installation of lightning protection and grounding systems across all Nuclear Island structures
  • Installation of welding network and socket circuits

Project by the Numbers:

7

individual civil structures within the Nuclear Island, where we performed our activities

115

kilometres of cables laid in primary cable routes

110

kilometres of cables installed in secondary cable routes + execution of secondary cable routes

193

delivered, installed and tested distribution boards and welding boxes

7426

installed lighting fixtures, including 1906 within the high-pressure containment zone

1200

tested circuits for working, backup and emergency lighting

8-10

designers handling lighting, lightning protection, lighting calculations, seismic studies, construction details, and site supervision

15

managerial staff (test engineers, inspection engineers, site managers, etc.)

80-100

installation workers on-site at peak